By 2030, Shandong will have initially established a new energy system

2026-11-23 19:59

On November 23, 2026, the Information Office of the People's Government of Shandong Province held a press conference to interpret the "15th Five Year Plan for the Construction of a New Energy System in Shandong Province" (hereinafter referred to as the "Plan").

Zheng Deyan, Secretary of the Party Group and Director of the Shandong Provincial Energy Bureau, stated that the overall goal of the "Plan" is to establish a clean, low-carbon, safe and efficient new energy system in Shandong by 2030; We have set up 18 quantifiable and implementable indicators in five categories: energy security, green transformation, carbon reduction and efficiency improvement, innovative development, and benefiting the people.

According to the Plan, after five years of development, it is expected that the energy system in Shandong will exhibit four characteristics, including stronger safety resilience, better energy structure, higher system efficiency, and stronger innovation vitality. Among them, the comprehensive energy production capacity within the province has reached 180 million tons of standard coal, and the support and guarantee of energy outside the province are strong. The supply structure is diverse and controllable, and the energy supply is reasonable and abundant. The proportion of non fossil energy consumption has reached over 20%, the proportion of non fossil energy installed capacity has increased to 60%, and the proportion of power generation has reached 40%, achieving both quantity and quality improvement.

In addition, Shandong will adhere to comprehensive planning and encourage regional leadership, focusing on the "Jinan Urban Circle Green Energy Corridor" and "Qingdao Urban Circle Modern Energy Bay Area", accelerating the construction of the "four highlands", namely the clean energy development highland on the eastern coast, the safe and reliable fossil energy storage and transportation highland, the important energy technology innovation highland in the country, and the energy equipment manufacturing highland in the northern region, creating a development pattern of "dual core leadership, multi-point support, and coordinated linkage", and initially building a clean, low-carbon, safe, and efficient new energy system.

In terms of building the foundation for the construction of a new energy system, Shandong will focus on the key links of "source, grid, and regulation", and promote the high-quality development and consumption of nuclear, wind, solar and other resources, with an annual increase of more than 10 million kilowatts of installed capacity; Building a new architecture for efficient collaborative power grid with main distribution microgrids, enhancing the reliable support of the new power grid; Construct pumped storage, compressed air, electrochemical and other energy storage facilities according to local conditions, with an average annual increase of over 3 million kilowatts. By 2030, the installed capacity of non fossil energy power generation in Shandong will reach around 200 million kilowatts.

At the same time, Shandong will integrate a new batch of ultra supercritical coal-fired power units with a capacity of 600000 kilowatts or more through measures such as relocating from urban areas to suburban areas and constructing new projects on site, in order to improve the reliability of power supply.

The construction of a new energy system cannot be separated from the support of a new power system. Liu Xuejun, Deputy Director of Shandong Energy Bureau, stated that during the 15th Five Year Plan period, Shandong will promote the construction of a new power system according to the overall layout of "3+3+3", focusing on streamlining the "power generation, transmission, and consumption" chain, so that power sources can be generated, the power grid can be delivered, and users can use them well.

Among them, on the power grid side, Shandong will strengthen the coordination between the main and distribution microgrids. By 2030, the 500 kV power grid will form a "six horizontal and six vertical" ring network, and the distribution network can carry 75 million kilowatts of distributed new energy, fully adapting to large-scale grid connection of high proportion new energy, and building a solid foundation for electricity security in the whole province.

Shandong will also activate diverse resources, promote the construction of pumped storage power stations in stages, diversify the layout of new energy storage, deeply tap into load side flexible regulation resources, and continuously improve the system's flexible regulation capabilities; By 2030, the operating pumped storage capacity will be around 8 million kilowatts, the new energy storage capacity will be around 30 million kilowatts, and the adjustable scale of virtual power plants will be over 4 million kilowatts.