The Fangcheng Port area of Beibu Gulf Port has made phased progress in the river sea intermodal terminal project

2026-10-21 22:27

Economic Observation Network According to the CCTV News client, recently, with the last caisson accurately and smoothly placed on the foundation, the installation of all caissons for the first phase of the river sea intermodal terminal project in the fourth operation area of the Fangcheng Port area of Beibu Gulf Port has been successfully completed. This marks the end of the key underwater control process of the project and a major milestone victory in the construction of the dock hydraulic main body, laying a solid foundation for the full sprint to the completion node of the dock hydraulic and road yard main body by the end of 2026.

As the "foundation" of the dock, the caisson is the "anchor" of engineering guarantee, and its installation quality directly determines the overall stability and operational safety of the dock. The transportation and installation of caissons belong to high-risk and hazardous projects at sea, and the construction is significantly constrained by marine environmental conditions such as tides, waves, and currents. The 1-2 berths of the completed caisson installation this time adopt a shore wall caisson structure, while the 7-10 berths adopt a "caisson gravity pier+high pile pier" structure, and the revetment adopts a gravity caisson structure.

As a key supporting project for the Western Land Sea New Corridor and the Pinglu Canal River Sea Intermodal Transport System, this project is located on the north side of berth 407 in the Yuhao Port area, with the construction of six 10000 ton bulk cargo berths. The total length of the dock shoreline is 1010.7 meters, and the designed annual throughput capacity is 19.2 million tons. It mainly handles bulk cargo such as coal, iron ore, bauxite, limestone, etc. As of now, the project has completed 59% of the estimated investment. After the installation of all the caissons is completed, the project will fully shift to the construction of the upper hydraulic structure, accelerate the construction of supporting facilities in the rear land area, and coordinate the progress of process equipment supervision and docking work.

After the completion of this project, it will fully leverage the advantages of the Pinglu Canal connecting the river and the sea, further improve the bulk cargo loading and unloading system of the Beibu Gulf Port, enhance the port's bulk cargo distribution capacity, ensure the transportation needs of port related industries, enhance the comprehensive service level of the Beibu Gulf International Gateway Port, better serve major national strategies, and inject strong momentum into the high-level construction of a new western land sea channel and the development and growth of the maritime economy.